Project Juliana Canal

Juliana Canal: a challenge to keep everything logistically safe

 

On behalf of Rijkswaterstaat, contractor Van den Herik-Sliedrecht is working on deepening and widening 4 kilometres of the Juliana Canal between Berg aan de Maas and Born. The project is so big that it is divided into three work sections; North, Middle and South. Jac Rijk was asked for the earthmoving work in the 1.5-kilometre-long Midden work section.

"Limburg is not unknown territory for us. We are familiar with the specific foundation and soil conditions. The latter is quite an issue with the Juliana Canal. It was once built on the existing ground level and in a different way than is done today." Speaking is Anders Ooms, project manager at Jac Rijk. With a small team of four men, he manages everything around earthmoving in work section Midden. "We have done many large earthmoving projects together with Van den Herik. In 2018, for example, we worked together on the widening of the Juliana Canal near Elsloo."

Family business

Family business Jac Rijk, as Anders describes it, has been on the road for quite a while. Founded in 1933, the third generation is now at the helm. Originally, the company operates in the world of earthmoving, mineral extraction, hydraulic works, road and dyke construction. The projects they are involved in go far beyond our national borders. From Bauxite excavation in Suriname and road construction in Africa to beach replenishment in Taiwan. Closer to home, Jac Rijk is involved in the construction of Maasvlakte II, a dyke improvement project in Breskens and, in a more distant past, the old ENCI limestone quarry near Maastricht.

Getting started with work plan

In April 2024, Anders started work with his team, with Van den Herik asking them 'Do you want to make a work plan for the earthmoving in the Middenvak?' This work plan included construction of the work road, construction of the driveway into the canal, phased excavation of the embankments, profiling of the embankments, installation of bentonite mats and the installation of the quarry stone. "It involves all facets of earthwork. A lot of cubic metres in a short time, but also hydraulically rebuilding a high-quality product to get a watertight channel. That presents challenges. There has always been talk of a waterproofing layer. We are building in such a way that it will be virtually watertight. That's how high the bar is set. Together we are working towards it lasting well over a hundred years."

Three goals

Within the project, there are three main goals: safety, quality and speed. "That last one, speed, actually contradicts the other two. But it was requested. That makes it a challenge to logistically keep everything as safe as possible. That you put down quality work and still with the speed that is demanded and the time pressure behind it to finish on time. The trick is to get everything done planning-wise so that the water can flow back into the Juliana Canal in April 2025."

Narrow work area, many transport movements

Within the theme of safety, Jac Rijk chose to build a central carriageway 12 metres wide. This is wide enough for two trucks to pass each other safely. The traffic also has fixed routes and one-way traffic has been applied. This keeps cross traffic to a minimum. These measures are no luxury. "The middle section is a fairly narrow section less than 40 metres wide, within which a lot of soil has to be transported. So we are dealing with a lot of cubic metres of soil and transport movements. At the peak of the work, there were about 600 transport movements a day in a 1.5-kilometre-long work section. On the busiest days at the end of 2024, we were working in the canal with 38 machines in the middle section." Anders therefore consults with his people on a daily basis: Who is working today? What work is crossing each other?

Different soil flows

In terms of quality, the different soil flows required a lot of attention. Prior to the work, thorough soil testing was carried out in the middle section. This included a distinction between industrially contaminated soil, category 1 clay, gravel and sandy material.

"These different soil streams must be excavated separately and disposed of at the appropriate depots. We also have to ensure that everything is delivered in separate soil streams. In total, we moved 240,000 m3 of soil for which we had limited depot space. The challenge was to be able to salvage everything."

Striking differences between work sections Striking were the differences in soil conditions on the more than 4 kilometres long section. In section North they found a lot of polluted silt, in section South the soil consisted mainly of sand and in section Middle the soil was relatively hard with a lot of gravel. "Gravel is beneficial for water management in view of the wet period, autumn and winter, during which we are working. Thanks to the gravel, most of the rainwater soaks into the ground. That benefits us. In addition, there was a fault line in the middle, where the groundwater level was a lot lower than in South.
On the fault line, we found mainly more sandy clay."

Cooperation

Jac Rijk is working as a subcontractor. And a flexible attitude is required of subcontractors. "That is also Jac Rijk's strength. We are dynamic and move with what is happening at the time. On the Julianakanaal project, we work with a small project team of four people. As an example of fast switching, Anders cites the good cooperation between the North, Central and South sections. "The earthmoving was reasonably smooth and problem-free in our section. This allowed us to assist in section North, where a lot of silt had to be excavated and removed. For the sake of the team, you support each other where and when necessary."

Forging a team together

Anders experiences the Juliana canal as a special project where dry earthmoving, hydraulic earthmoving and stone construction come together. "This is where the expertise of our people comes to the fore and where we can show what we have to offer. We have quite a lot of machinists in house, but we could not do this alone. The challenge was to forge a good team in a very short time with professionals from other contractors we work with. Right from the moment Van den Herik invited us, we set our lines and put together the team we thought we needed. And if that then works out and everyone understands each other and is working well, that is very decisive in making a beautiful job."